District Development Updates

District Development Updates share information on planned, ongoing, and completed projects within the Skyway Marina District. This page highlights public and private improvements, redevelopment efforts, and infrastructure changes shaping our waterfront—helping residents and businesses stay informed as the district continues to grow and evolve.
The Skyway Marina District is not the developer or project owner but serves as a community liaison and information-sharing resource.Keeping the community up-to-date with confirmed information from within the Skyway Marina District.

Upcoming Projects

SPC Allstate: Kolter Group

Upscale Senior Living & Retail Strip - 4537 34th St. S. & 4401 34th St. S.

Planned:  Start Date: 2nd QTR 2021 – The upscale senior living facility will have 154 units for both independent and senior living. It will be an eight story building directly facing Boca Ciega Bay. The retail strip will be located at the front of the property aligning 34th Street South next to McDonald’s.

Completed:  Purchased southern and middle parcel’s of the old “Shopping Mall” strip located on 34th Street South.

The Manhattan – In Progress

BayCare Urgent Care Center - 4000 34th St S

Completed: BayCare leased for Urgent Care – no set date.

Planned:  Re-development of the site to a BayCare Urgent Care Center – Time frame: N/A

BayCare Subleasing for medical use only (no plan of BayCare redevelopment

Former Bob Evans Restaurant

Completed: Demolition In Progress: Mavis Brake & Tire

Current Projects

Altis Cardinal: Sky Town

RETAIL SKYTOWN

Completed Projects

Marina Walk - 4601 34th St S

Current owners – re-developing the site of the Flamingo Resort. Property was not sold to a developer.

In-Progress: Construction of 245 Luxury Apartments and front parcel to include Starbucks, Tropical Smoothie, and TBD construction

Completed: Demolition of the Flamingo Resort.

Planned: Completion date of 2021.

Completed

Current owners – re-developing the site of the Flamingo Resort. Property was not sold to a developer.

In-Progress: Construction of 245 Luxury Apartments and front parcel to include Starbucks, Tropical Smoothie, and TBD construction

Completed: Demolition of the Flamingo Resort.

Planned: Completion date of 2021.

Completed

Current owners – re-developing the site of the Flamingo Resort. Property was not sold to a developer.

In-Progress: Construction of 245 Luxury Apartments and front parcel to include Starbucks, Tropical Smoothie, and TBD construction

Completed: Demolition of the Flamingo Resort.

Planned: Completion date of 2021.

Completed

Current owners – re-developing the site of the Flamingo Resort. Property was not sold to a developer.

In-Progress: Construction of 245 Luxury Apartments and front parcel to include Starbucks, Tropical Smoothie, and TBD construction

Completed: Demolition of the Flamingo Resort.

Planned: Completion date of 2021.

Completed

Woody's Wash Shack - 3401 34th St S

Current owners – re-developing the site of the Flamingo Resort. Property was not sold to a developer.

In-Progress: Construction of 245 Luxury Apartments and front parcel to include Starbucks, Tropical Smoothie, and TBD construction

Completed: Demolition of the Flamingo Resort.

Planned: Completion date of 2021.

Completed

Current owners – re-developing the site of the Flamingo Resort. Property was not sold to a developer.

In-Progress: Construction of 245 Luxury Apartments and front parcel to include Starbucks, Tropical Smoothie, and TBD construction

Completed: Demolition of the Flamingo Resort.

Planned: Completion date of 2021.

Completed

Current owners – re-developing the site of the Flamingo Resort. Property was not sold to a developer.

In-Progress: Construction of 245 Luxury Apartments and front parcel to include Starbucks, Tropical Smoothie, and TBD construction

Completed: Demolition of the Flamingo Resort.

Planned: Completion date of 2021.

Completed

Facts

The More You Know

Franchises:  Franchise Restaurants are not interested in the area, until the area meets their scope. Meaning the increase of people and income. Most restaurants (franchise/name brand) will not sign up to lease until about 6 month prior to the housing being finished.  Restaurants do not want to be open during a construction site.  Restaurants do not want to open without the people to patronize them.  It will happen, just in time.  Due to COVID and the change in employment in hospitality, restaurants are not building new, as the ROI is non obtainable.  Cost of building and lack of employees as of now will keep new restaurants from being built.

Home Improvement Stores:  The “orange” and “blue” businesses are NOT building new stores.

Department Stores:  These businesses, just like the restaurants, say we do not meet the scope of their income base or resident amount.  More people = more opportunity for companies to view the area as a possibility. With time, this will change.. Our income/residency is growing, and we are becoming more visible – We are working with developers to increase the retail in the SMD.